Photo of white lines on roadWorking Group Objectives:

Review of all Highways related projects and establishing close liaison with Dorset Council Highways.

Working Group Participants:

Andrew Huggins (Chair), Ken Morgan, Alf Bush, Peter Webb, Beverly Barker, Rob Aspray

Dependencies:

DC Highways approval and partial funding

Status/Next Steps:

  • School Crossing – Highways have been given the green light to proceed with the Zebra crossing proposal, subject to various checks, audits, orders, etc. Probably Easter 2024 for installation.
  • Huntick Road Cycleway – apply for approval for next section – Rozalia Meadows to Jubilee Walk
  • High Street Crossing – apply for permission to install as a ‘place’ project.
  • Tesco Island – Create formal notice to Tesco of intentions with DCH approval.
  • 20 MPH Zones – Apply for central village area to be set to 20 mph.
  • Drop kerbs

Budget

Financial Forecast:

(£000’s, excluding VAT)

2023-24 2024-25 2025-26
Expense to date
Forecast 2551 802 1,0003
Total 255 80 1,000

Notes:

  1. School crossing – 100,000, High St crossing 75,000, 20MPH – 30,000, Drop kerbs – 15,000, Huntick cycleway stage 2 – 35,000
  2. Tesco forecourt – 80,000
  3. Huntick cycleway stage 3 – 1,000,000

 

Highways Working Group June 23 Update