Working Group Objectives:
Review of all Highways related projects and establishing close liaison with Dorset Council Highways.
Working Group Participants:
Andrew Huggins (Chair), Ken Morgan, Alf Bush, Peter Webb, Beverly Barker, Rob Aspray
Dependencies:
DC Highways approval and partial funding
Status/Next Steps:
- School Crossing – Highways have been given the green light to proceed with the Zebra crossing proposal, subject to various checks, audits, orders, etc. Probably Easter 2024 for installation.
- Huntick Road Cycleway – apply for approval for next section – Rozalia Meadows to Jubilee Walk
- High Street Crossing – apply for permission to install as a ‘place’ project.
- Tesco Island – Create formal notice to Tesco of intentions with DCH approval.
- 20 MPH Zones – Apply for central village area to be set to 20 mph.
- Drop kerbs
Budget
Financial Forecast:
(£000’s, excluding VAT) |
2023-24 | 2024-25 | 2025-26 |
Expense to date | |||
Forecast | 2551 | 802 | 1,0003 |
Total | 255 | 80 | 1,000 |
Notes:
- School crossing – 100,000, High St crossing 75,000, 20MPH – 30,000, Drop kerbs – 15,000, Huntick cycleway stage 2 – 35,000
- Tesco forecourt – 80,000
- Huntick cycleway stage 3 – 1,000,000
Highways Working Group June 23 Update